< Back to All Stakeholder Questions and Answers

When setting up resources and constraints for the model, do you include cost assumptions as part of the model, including that resources might become cheaper over time?

As stated in previously-posted Q&A, the Company uses a combination of internal subject matter expert experience and industry data to develop costs for future projects.

Additional discussion on IRP costs, including commodity price forecasts, is available in the meeting materials from IRP Conference 1 and IRP Conference 2.