Stakeholder Process Information
Meetings & Materials
Stakeholder Q&A
Submit Feedback
< Back to All Stakeholder Questions and Answers
With the increase of data center load, how does it affect the demand for transmission, substations, and power generation investments.
The company expects to deploy more than
$40 billion
in capital over the next five years to support one of the highest projected growth rates of any utility and enable its “all-of-the-above” approach to resource adequacy, ensure reliable and increasingly clean energy supplies, and continue to
maintain
its assets. Slides 8 through 10 of the presentation discussed at the 2025 IRP Update Stakeholder Meeting
regarding
Modeling held on August 27
th
,
including
information
regarding
the load forecast
.
In addition, Section
2
.1
and Appendix 2A of the 2024 IRP provide extensive information on the load forecast, load growth, and the data center contribution to that load growth, as well as extensive written and verbal testimony from the 2024 IRP
p
roceeding
which is available on the
State
Corporation Commission
website.
Other Stakeholder Questions and Answers
How is the combination of solar and storage considered?
Will you incorporate any of the elements of the SCC's 2024 IRP Final Order in the 2025 IRP update? Please provide an explanation of how you will comply with each of these requirements, both in the update and in the 2026 filing.