Why are there not ELCC values from PJM for solar plus storage? Why is solar plus storage not in the model, since we have solar plus storage at Dulles?

PJM models solar and storage resources independentlyIt is assumed Dulles will participate as a co-located resource, which means it would effectively participate as two separate resources in the PJM marketThat is consistent with how we have modeled solar and storage resources in the PLEXOS model.