Stakeholder Process Information
Meetings & Materials
Stakeholder Q&A
Submit Feedback
< Back to All Stakeholder Questions and Answers
Please provide a map of transmission lines in Dominion Energy territory superimposing (a) current MW capacity of each line and (b) forecast data center load increases.
Dominion Energy has approximately
6,800 miles
of transmission lines in Virginia, North Carolina, and West Virginia at voltages ranging from 69 kV to 500 kV
.
A map of those lines was published on page 23 of the Company’s 2024 IRP
.
Transmission planning occurs on the regional level
pursuant to
PJM’s Manual 14B: PJM Transmission Planning Process (
https://www.pjm.com/-/media/DotCom/documents/manuals/m14b.pdf
) and under the Federal Energy Regulatory Commission’s (“FERC”)
jurisdiction
, which requires clear functional separation between power generation and transmission planning to ensure fair and efficient operation of the electric grid.
Other Stakeholder Questions and Answers
Will you incorporate any of the elements of the SCC's 2024 IRP Final Order in the 2025 IRP update? Please provide an explanation of how you will comply with each of these requirements, both in the update and in the 2026 filing.
How are the three levels of contracts used to produce the load forecast? Specifically, ESA, SELOA, and CLOA contracts. When data centers are not yet approved by localities, but SELOA's have been signed, are those included in the load forecast?