Does the Company have any updates on when construction of a small modular reactor may begin at North Anna?

The earliest construction activity would likely occur in the late 2020s, given the time needed for commissioning, testing, and a typical 3–4-year construction period. However, no commitment has been made to build an SMR at North Anna, and the project remains in the feasibility evaluation stage with no NRC filings submitted.