Can Dominion Energy share more information on the capacity that advanced conductors can provide?

A qualitative discussion on advanced conductors and other grid enhancing technologies will be included in this year’s IRP. It is important to note, the installation of a new transmission line and the amount of additional load that can be served in a particular load zone depends on the next most limiting network componentsTransmission is not a radial distribution network that by adding an 84MVA TX you add 84 MVA of capacity to the network.