Please provide a list of existing power generation by geographic location and by amount of generation. Please explain how that relates to the Dominion Energy load forecast. What is the aggregate shortfall in power generation?
Please see Appendix 3B-1 of the 2024 IRP for a list of the Company's generating units. Please see Appendix 3C-5 of the 2024 IRP for the actual (2021-2023) and projected (2024-2039) Summer Capacity Position.
Other Stakeholder Questions and Answers
Please provide information on how cost impacts are modeled and presented in the Integrated Resource Plan.
How much of the load forecast increase from 2024 to 2025 is for data centers and how is the data center load split between the Dominion Load Serving Entity (LSE) and other LSEs? Where in VA is the data center load increasing? What process does Dominion use for load requests, and how does that eliminate double counting in the load requests?