How many years does this stakeholder modeling scenario cover? Would a 20-year time horizon go from 2026 to 2046?
For all plans, we will be
using
a
20-year
planning horizon
. It will show resource add
itions
or retirements
that occur between 2026 and 2045.
This includes a full plan for 2026 and 2045, making that a 20-year horizon.