Stakeholder Process Information
Meetings & Materials
Stakeholder Q&A
Submit Feedback
< Back to All Stakeholder Questions and Answers
How are the three levels of contracts used to produce the load forecast? Specifically, ESA, SELOA, and CLOA contracts. When data centers are not yet approved by localities, but SELOA's have been signed, are those included in the load forecast?
The company does not forecast by contract. Contracts are used to
validate
the forecast.
Other Stakeholder Questions and Answers
Please provide a map of transmission lines in Dominion Energy territory superimposing (a) current MW capacity of each line and (b) forecast data center load increases.
Does the DOM Zone forecast include data center load growth from coops such as NOVEC and REC?