How are the three levels of contracts used to produce the load forecast? Specifically, ESA, SELOA, and CLOA contracts. When data centers are not yet approved by localities, but SELOA's have been signed, are those included in the load forecast?
The company does not forecast by contract. Contracts are used to
validate
the forecast.